{"id":2465,"date":"2021-07-08T09:50:03","date_gmt":"2021-07-08T01:50:03","guid":{"rendered":"https:\/\/www.bjwlx.com\/?p=2465"},"modified":"2021-10-09T17:52:23","modified_gmt":"2021-10-09T09:52:23","slug":"%e9%92%a2%e7%ad%8b%e6%96%bd%e5%b7%a5%e5%90%84%e7%8e%af%e8%8a%82%e5%ae%9e%e6%93%8d%e8%a6%81%e7%82%b9%e6%80%bb%e7%bb%93%ef%bc%8c%e5%80%bc%e5%be%97%e6%94%b6%e8%97%8f%ef%bc%81","status":"publish","type":"post","link":"https:\/\/www.bjwlx.com\/en\/?p=2465","title":{"rendered":"Summary of practical operation points of each link of reinforcement construction, which is worth collecting!"},"content":{"rendered":"

 <\/p>\n

 <\/p>\n

Reinforcement engineering is an extremely important project in building construction. Its construction quality is the key to determine the quality of building structure, and will also affect the follow-up project construction. Civil engineering Jun has previously shared the treatment of common problems in reinforcement construction quality, and learned that solving problems is not enough, but more importantly, prevention. Standardize the construction, eliminate quality problems and reduce the waste of labor, time and materials.<\/p>\n

Today, the key points of practical operation are summarized from the aspects of reinforcement construction preparation, material saving, testing, construction, anti-corrosion and acceptance. Full of dry goods:<\/p>\n

 <\/p>\n

\"\"<\/p>\n

 <\/p>\n

 <\/p>\n

Construction preparation<\/h2>\n

1. During construction, be familiar with the construction drawings and relevant changes, and fill in the review records and changes in the corresponding positions in the construction drawings to prevent errors during construction.<\/p>\n

2. After being familiar with the construction drawings and before construction, the setting out table of reinforcement shall be completed first, the steel consumption plan shall be provided to the project department, and the problems occurred in the setting out process shall be reported to the technical director of the project department in time.<\/p>\n

3. Cooperate with the foreman of the project department in technical disclosure and safety education at all levels.<\/p>\n

4. The certificates of the operators for butt welding and vertical welding of reinforcement shall be provided to the project department for filing in time to complete the simulated welding test, etc. Actively cooperate with the project department to witness and take reinforcement materials.<\/p>\n

5. All materials entering the site shall be classified, stacked and identified, and materials that have not been inspected are strictly prohibited from use.<\/p>\n

 <\/p>\n

Key points of material saving<\/h2>\n

1. In the procurement stage, the actual use of reinforcement raw materials in each stage, the scale of reinforcement stacking yard, the existing surplus reinforcement and surplus materials on site shall be comprehensively considered, so as to formulate the optimal reinforcement procurement plan, and select the appropriate reinforcement length according to the blanking sheet and the actual situation of the site.<\/p>\n

2. Reinforcement processing shall be carried out in batches. It is not allowed to make and bind components one by one, and each batch shall be a construction section not less than 30m long, so as not to affect the project progress, or cause a large waste of materials and serious slowdown.<\/p>\n

3. During construction, the head of reinforcement shall be cleaned first, classified according to the thickness and length, and placed from one end.<\/p>\n

4. During construction, unified allocation management shall be carried out for the use of reinforcement, a quota picking system shall be established, and materials shall be distributed in strict accordance with the principle of “first in, first out, pushing the old and storing the new”.<\/p>\n

5. During construction, long materials shall be used or intercepted first, and then the remaining short materials shall be used reasonably. It is not allowed to use overqualified materials, superior materials and inferior materials. If there is any lost reinforcement, it shall be preferentially used for horse stool reinforcement, embedded parts, short hole reinforcement, etc., and the long and short head reinforcement can be welded together, so as to greatly save the amount of reinforcement.<\/p>\n

6. After construction, if there are still remaining reinforcement heads or semi-finished products, the materials shall be recorded in the account, the use of steel shall be checked regularly, and the loss rate shall be checked, so that the next material selection shall give priority to the selection and use of head materials, and then the reinforcement raw materials shall be selected.<\/p>\n

 <\/p>\n

\"\"<\/p>\n

Key points of detection<\/h2>\n

Reinforcement source detection<\/p>\n

(1) The construction unit shall issue the following quality certificates:<\/p>\n