Project overview
Application of PC construction method pile
Construction method of composite steel pipe pile with PC construction method
1) The first section of steel pipe pile and Larsen steel sheet pile sinking equipment adopts Hitachi 470h crawler full hydraulic full swing long arm vibrating hammer (hydraulic long arm vibrating hammer). The equipment has large operation radius and flexible loading, can freely adjust the direction and verticality of steel pipe piles, and has high construction efficiency.
2) During the construction of section 2 steel pipe pile, crawler crane and 28rf electric vibrating hammer shall be used for pile sinking. The maximum exciting force of the vibrating hammer is 786kn and the pile pulling force is 400kN, which can fully meet the construction needs of the project.
3) The PC construction method combined steel pipe pile at the corresponding position shall be constructed with ice 28rf resonance free hammer. This type is a high-frequency vibrating hammer with low construction noise and little impact on the surrounding soil, which can realize pollution-free construction.
1) Measurement and setting out. According to the survey control network of the project, the center line of the row of piles shall be determined first, then the center position of the first steel pipe pile shall be determined, and the construction shall be carried out along the center line according to the construction sequence. The axis measurement and setting out shall be reported to the supervising engineer for review and confirmation after review.
2) Alignment and verticality calibration of pile position. The key of pile position alignment is to ensure that the pile row construction position is on the positioning center line. Before construction, a theodolite shall be erected on the center line of the row of piles, about 25m away from the construction pile position, and the verticality of the steel pipe pile and the center position of the guide groove shall be observed from the angle of the center line, so as to ensure the verticality and avoid the center position of the row of piles from exceeding the axis position. In addition, another theodolite shall be erected at the position where the first theodolite forms an angle of about 90 ° with the pile position to check the verticality deviation. First lift the section 1 pile and insert it into the underground arranged pile position. First insert it into the soil for 30 ~ 50cm. After the insertion is stable, use two theodolites to carry out vertical correction at the same time until the verticality of the pile meets the specification requirements (the vertical correction shall not be carried out after the pile is driven into the soil for 3M. If there is any deviation, it shall be pulled out and re inserted).
3) Positioning and verticality control of the first pile construction. Because the size adjustment of the guide groove connected between the steel pipe pile and Larsen steel sheet pile is limited in the transverse direction, and the guide groove is consistent with the center line of the row of piles, the positioning and verticality control of the first pile is particularly critical.
4) Section 1 steel pipe pile sinking. Section 1 after the alignment and perpendicularity of steel pipe pile (lower section) are corrected, the crawler type full hydraulic full rotation long arm vibrating hammer (hydraulic long arm vibrating hammer) shall be used for vibration driving. Firstly, the pile weight and hydraulic vibrating hammer weight shall be pressed down. After the pile sinking is stable, the vibrating hammer shall be started, and the working arm shall continue to press down and drive by vibration until the upper end of the steel pipe is about 1m away from the bottom of the groove. During pressing and vibration driving, use two theodolites to observe the perpendicularity.
5) Connection of steel pipe piles. The 2m long inner liner pipe is used as the connecting medium material at the butt joint of steel pipe pile to strengthen the lateral stiffness of the joint and facilitate the butt welding of steel pipe. There are 12 holes at both ends of the inner liner pipe, and there are also 12 holes at the connecting end of the upper and lower steel pipes corresponding to the holes of the inner liner pipe. They are connected with the inner liner pipe with high-strength bolts to temporarily fix each component (inner liner pipe, upper and lower steel pipes) before welding. The welding quality shall be ensured during butt welding, and the weld shall be full. In order to ensure that the upper and lower energy-saving steel pipe piles are pulled out smoothly, four 20cm steel pipes are welded at the connection between the upper and lower steel pipes × 20cm arc steel plate. All four sides of the steel plate shall be welded and the weld shall be full.
6) Section 2 steel pipe pile sinking. Since it cannot be processed at one time, the pipe pile shall be welded first and driven underground after cooling.
7) Larsen steel sheet pile sinking. After the steel pipe pile is sunk to the design elevation, the long arm vibrating hammer lifts the Larsen steel sheet pile, aligns with the connecting lock port of the steel pipe side wall, vibrates and sinks, corrects the verticality and the center line of the Larsen steel sheet pile in the direction of the pile row axis, and vibrates and sinks to the design elevation after meeting the design requirements.
8) Closure of row piles. The combined steel pipe pile row piles of PC construction method are constructed along the axis direction. When they are closed at the end, there are inevitably dimensional deviation and perpendicularity deviation of the closure section, and the regulated steel pipe piles or Larsen steel sheet piles cannot be closed smoothly. At this time, steel plate latch plane connection can be adopted.
reference:
[1] Chen Shengxian, Xu quanbiao. Application of PC construction method pile in foundation pit engineering of a project in Deqing [J]. Shanxi architecture, 2016, 42 (33): 8041
[2] yuan Jiao, Zheng Mingxin, Wu Gang. Comprehensive analysis of pit support problems in a deep foundation pit project [1]. Construction technology, 2016, 45 (17): 25-28
Source: Baidu Library
For communication and learning only
If there is infringement, please contact to delete